Light rail in Canberra

From Wikipedia, the free encyclopedia

Canberra light rail network
An Urbos 3 departing Alinga Street
An Urbos 3 departing Alinga Street
Overview
LocaleCanberra, Australian Capital Territory
Transit typeLight rail
Number of lines1
Line numberR1
Number of stations14 (3 under construction)
Annual ridership4,104,388 (2023)[1]
HeadquartersMitchell
Websitecmet.com.au
Operation
Began operation20 April 2019
Operator(s)Canberra Metro Operations (CMET)
Number of vehicles19 CAF Urbos 3 trams
Train length32.96 m (108.1 ft)
Headway5-15 minutes
Technical
System length12 km (7.5 mi)
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification750 V DC overhead catenary
Top speed70 km/h (43 mph)

The Canberra light rail line serves the city of Canberra, Australia. The initial 12-kilometre (7.5 mi) light rail line links the northern town centre of Gungahlin to the city centre (Civic) and has 14 stops. Services commenced on 20 April 2019. The 14th stop at Sandford Street in Mitchell commenced operation in September 2021.[2]

An extension from Civic to Commonwealth Park (Stage 2A) is under construction and is expected to be operational in early 2028.[3] Planning of a further extension from Commonwealth Park to Woden Town Centre (Stage 2B) will continue while construction of Stage 2A is underway.[4]

History

[edit]

Background

[edit]
Aerial view of Northbourne Avenue, 2009, before construction of the light rail. Seen looking north from Civic, with City Hill in the foreground.

Walter Burley Griffin's master plan for Canberra proposed the construction of a tram network and a heavy rail line.[5][6] However, excepting for the Canberra station, the city was exclusively served by buses from the 1926 introduction of the Canberra City Omnibus Service until the 2019 opening of light rail services.

In 1988, Comeng proposed a Light Rail system for Canberra.[7] One line was proposed in three stages - Woden-City-Belconnen (about 18km), Woden-Tuggeranong (about 11.5km), and Belconnen-Kippax Centre (about 5.8km).[7]: 10 (PDF 14) 

Government proposals before 2012 ACT election

[edit]

In 1994, the Labor-led ACT Government commissioned a study into light rail, based on the findings of an independent report that light rail would be viable in Canberra by 1998.[8] In its report, consultants Booz Allen Hamilton recommended a route from Belconnen to Barton via the City and Kings Avenue Bridge be operating by 1998; Woden to Barton by 2000; Tuggeranong to Woden by 2002; and Gungahlin to City by 2004. Routes to Canberra Airport and Queanbeyan received a lower priority. By January 1995, the Canberra Liberals announced their opposition to the light rail proposal, questioning the report's patronage figures and population projections for Canberra-Queanbeyan.[9] In March 1995, the Canberra Liberals came to power and plans for a light rail system were discontinued.

In February 1998, the Canberra Liberals announced its support for the Federation Line, a proposed 7-kilometre (4.3 mi) line from the National Museum of Australia via Civic to the Australian War Memorial. This line was proposed to use heritage trams.[10]

Proposal reached

[edit]

Following the 2012 ACT election, ACT Labor needed the ACT Greens' support to remain in government. As part of their coalition agreement, the two parties agreed to the construction of Stage 1 of the light rail.[11][12] Both parties had campaigned at the election in support of light rail.[13]

The opposition Canberra Liberals opposed the project. In April 2015, the party announced it would cancel any contracts for the light rail if it won the 2016 ACT election.[14] The light rail project was the major issue of the 2016 campaign.[15][16] The Labor government was returned at the election, with the party claiming the result as an endorsement of the project.[17]

Development and Stage 1

[edit]

In the 2013/14 ACT budget, $5 million was allocated for early design work.[18] In September 2014, the business case was approved by the government. The project, known as Capital Metro during planning, was developed by the government agency Capital Metro Agency (CMA). The line was to be delivered under a public-private partnership.[19][20]

Light rail works in Franklin in July 2017
The centre of Flemington Road in Gungahlin after being cleared for light rail works in July 2017

In February 2016, after a tender process, the government that Canberra Metro consortium was the preferred tenderer and finalised the contract in May that year.[21][22][23] Under the contract, Canberra Metro will operate and maintain the line for 20 years, after which ownership will pass to the ACT Government.[21][24]

Stacked rails in Gungahlin in August 2017

Design and construction costs were budgeted at $707 million.[21] The Federal Government contributed $67 million to the project.[24] Commencement of construction was marked by a sod-turning in the northern suburb of Mitchell at the site of the depot on 12 July 2016.[25] Major construction of the route itself began towards the end of the year.[26][27][28]

The CMA was amalgamated into a new government directorate, the Transport Canberra & City Services (TCCS), on 1 July 2016, resulting in the responsibility for the project being transferred to the TCCS.[29]

Testing of the line began in June 2018. A section in Gungahlin was electrified and one of the trams made trial runs.[30] The last tram arrived in Canberra in September 2018 and it was hoped to have the project completed by the end of 2018.[31] The light rail eventually opened on 20 April 2019, with the final construction cost for Stage 1 being $675 million, some $32 million under the original budget.[32][33][34]

Route

[edit]
The Phillip Avenue light rail stop
Each station has a ticket machine
The depot in Mitchell

The 12-kilometre (7.5 mi) line has its northern terminus at Hibberson Street in Gungahlin and follows Flemington Road, the Federal Highway and Northbourne Avenue to the southern terminus between Alinga and Rudd Streets in the City Centre. It is double track for its full length.[21] Emergency crossovers are located to the south of the Dickson Interchange stop, as well as the north of the Nullarbor Avenue stop.[35] There are 14 stops.[36] The main bus interchanges are located at Gungahlin Place, Dickson Interchange and Alinga Street.[21][37]

Map

Stops

[edit]
Diagram of R1 Canberra light rail (inclusive of Stage 2A)
Stop Suburb Platform layout Coordinates Refs.
Gungahlin Place Gungahlin Dual (Island & Side) 35°11′8.3″S 149°8′7.73″E / 35.185639°S 149.1354806°E / -35.185639; 149.1354806 (Gungahlin Place) [38]
Manning Clark North Gungahlin Island 35°11′13.15″S 149°8′36.14″E / 35.1869861°S 149.1433722°E / -35.1869861; 149.1433722 (Manning Clark North) [39]
Mapleton Avenue Franklin / Harrison Island 35°11′36.17″S 149°9′3.5″E / 35.1933806°S 149.150972°E / -35.1933806; 149.150972 (Mapleton Avenue) [40]
Nullarbor Avenue Franklin / Harrison Island 35°12′1.98″S 149°8′57.46″E / 35.2005500°S 149.1492944°E / -35.2005500; 149.1492944 (Nullarbor Avenue) [41]
Well Station Drive Mitchell Island 35°12′29.29″S 149°8′50.96″E / 35.2081361°S 149.1474889°E / -35.2081361; 149.1474889 (Well Station Drive) [42]
Sandford Street Mitchell Island 35°13′17.8″S 149°8′40.8″E / 35.221611°S 149.144667°E / -35.221611; 149.144667 (Sandford Street)
EPIC and Racecourse Lyneham Side 35°13′42.37″S 149°8′39.85″E / 35.2284361°S 149.1444028°E / -35.2284361; 149.1444028 (EPIC and Racecourse) [43]
Phillip Avenue Lyneham / Watson Island 35°14′8.86″S 149°8′38.14″E / 35.2357944°S 149.1439278°E / -35.2357944; 149.1439278 (Phillip Avenue) [44]
Swinden Street Lyneham / Downer Island 35°14′38.89″S 149°8′4.69″E / 35.2441361°S 149.1346361°E / -35.2441361; 149.1346361 (Swinden Street) [45]
Dickson Interchange Lyneham / Dickson Side 35°15′2.01″S 149°8′1.46″E / 35.2505583°S 149.1337389°E / -35.2505583; 149.1337389 (Dickson Interchange) [35]
Macarthur Avenue Lyneham / Dickson Side 35°15′36.57″S 149°7′56.02″E / 35.2601583°S 149.1322278°E / -35.2601583; 149.1322278 (Macarthur Avenue) [46]
Ipima Street Turner / Braddon Side 35°15′57.23″S 149°7′52.62″E / 35.2658972°S 149.1312833°E / -35.2658972; 149.1312833 (Ipima Street) [47]
Elouera Street Turner / Braddon Side 35°16′21.42″S 149°7′48.62″E / 35.2726167°S 149.1301722°E / -35.2726167; 149.1301722 (Elouera Street) [48]
Alinga Street Civic Side 35°16′40.56″S 149°7′45.59″E / 35.2779333°S 149.1293306°E / -35.2779333; 149.1293306 (Alinga Street) [49]

The Sandford Street light rail stop commenced construction in 2020 and opened on 16 September 2021.[50][51][2]

Operation

[edit]
Canberra Metro Operations logo

The service is operated by Canberra Metro Operations (CMET), in association with Deutsche Bahn Engineering and Consulting, under a 20-year contract.[21][52] CMET is a joint venture between John Holland and Pacific Partnerships, both of whom are part of the Canberra Metro consortium.

CMET holds the contract to operate the light rail until at least 2036.[53]: p. 1 [54] Formed in 2016,[55] it is a partnership between John Holland and Pacific Partnerships in association with Deutsche Bahn Engineering and Consulting.[53]: p. 12  CMET commenced operations on 20 April 2019 with the completion of the first stage of the project.[56]

The structure of the Canberra Metro Consortium[53]: p. 13 

CMET is part of the Canberra Metro Consortium, acting as the operations component of the group, with both its owners also being equity providers.[53]: p. 12  CMET does not contract with the ACT Government, rather it contracts with Canberra Metro PC Pty Limited (Canberra Metro) to provide service on its lines, which then contracts with the Canberra Metro Agency to manage the project and provide services to the city.[53]: p. 3 

The contract specifies the following minimum service levels for hours of operation and service frequency:[21]

Day First service Last service
Monday to Thursday 06:00 23:30
Friday and Saturday 06:00 01:00 the following day
Sunday 08:00 23:30
The last services from Gungahlin depart half an hour earlier.
The first service from the city on Sunday departs half an hour later.
Day Departure time Frequency
To the city To Gungahlin
Monday to Friday 06:00-07:00 15 minutes 15 minutes
Monday to Friday 07:00-07:30 6 minutes 10 minutes
Monday to Friday 07:30-09:00 6 minutes 6 minutes
Monday to Friday 09:00-16:00 10 minutes 10 minutes
Monday to Friday 16:00-17:30 6 minutes 6 minutes
Monday to Friday 17:30-18:00 10 minutes 6 minutes
Monday to Friday After 18:00 15 minutes 15 minutes
Saturday 06:00-01:00 15 minutes 15 minutes
Sunday 08:00-23:00 15 minutes 15 minutes

Rolling stock

[edit]
An Urbos 3 on Northbourne Avenue
Interior

14 CAF-built Urbos 3 trams operate on the system. CAF will also provide twenty years of maintenance for the fleet.[57][58] The trams are 32.96 m (108 ft 1.64 in) long and consist of five modules. There are four doors on each side of the vehicle, two single-leaf and two double-leaf doors.[59] The first tram was delivered in December 2017.[60][61][62] The vehicles feature a red and grey livery, with a white reflective stripe in the middle.[63] The depot is located in Mitchell.[64]

Five additional light rail vehicles were ordered from CAF ahead of the construction of Stage 2A. These vehicles are capable of wire-free running, as required by the National Capital Authority within its defined area. Deliveries began during 2024 and by January 2025, four were operational, with two in regular service.[65]

Control system

[edit]

Tehnika's t-visor RAIL platform, also used on the Gold Coast Light Rail,[66] provides the operators with a single, centralised control system. This encompasses the automatic vehicle location, traffic signalling priority, traction power & infrastructure SCADA, CCTV and passenger information systems, amongst others.[67]

Stage 2 extension

[edit]
View of Commonwealth Avenue looking south from City Hill towards Parliament House. The hump in the middle distance is the bridge over Lake Burley Griffin, between which trams will travel if Stage 2B goes ahead.

Background

[edit]

The consortia participating in the procurement process for the initial line were asked to develop plans for an expanded route from the City Centre to the Defence headquarters in Russell via London Circuit and Constitution Avenue. This additional 3.2-kilometre (2.0 mi) section was estimated to boost the patronage of the line as a whole by more than 30%. The proposal highlighted the desire of the Federal Government's National Capital Authority to use wire-free technology to power the trams in areas of the city under the authority's management.[68][69]

The ACT Government decided not to proceed with the expanded route but committed to releasing a plan for a second stage of the light rail network (known as Stage 2) before the October 2016 territory election. It was considering extending the line not only to Russell but to the broader parliamentary triangle, possibly including Canberra Airport and the Australian National University.[70]

Development of route and funding

[edit]

In July 2016, the government released a shortlist of four potential routes that could form the second stage of the light rail network. The routes were:[71]

In September 2016, the government selected a truncated version of the Mawson route that ends at Woden as its preferred second-stage project.[72][73] At that stage, the only firm decisions the government had made about the route were that it would run from Alinga Street to the Woden Town Centre and use Commonwealth Avenue Bridge to cross Lake Burley Griffin.[74]

In July 2019, the ACT Transport minister Chris Steel announced that Stage 2 would be divided into two parts: Stage 2A from Civic to Commonwealth Park just before Lake Burley Griffin, and Stage 2B to continue from Commonwealth Park to Woden across the lake.[75]

Stage 2A

[edit]
Parts of Stage 2A will contain green track. This is the prototype being tested at the National Arboretum

Business case

[edit]

In September 2019, the ACT Government approved the business case for Stage 2A, confirming the three new stops on the route and the requirement for London Circuit to be raised at Commonwealth Avenue where the light rail will travel.[76][77] According to the Stage 2A business case released the same month, from the Alinga Street Stop to the Commonwealth Park Stop will be about 6 minutes.[78] This business case estimated that the stage would deliver an estimated $150 million in benefits, but with a capital cost of an estimated $268 million.[79]

At the 2020 ACT election, the opposition Canberra Liberals expressed in-principle support for Stage 2, but did not commit to continuing the project.[80][81] With the re-election of the Labor government at the election, Chief Minister Barr claimed a renewed mandate to continue Stage 2.[82]

Ongoing construction

[edit]

In November 2022, works to raise London Circuit commenced.[83][84] These works reached "practical completion" in August 2025.[85]

Light Rail Stage 2A works on the intersection of London Circuit and Northbourne Avenue in Civic during January 2026

In late 2024, wire-free rail vehicles began to be used on the Stage 1 route, in preparation for their use once the Stage 2A extension becomes operational.[65]

In February 2025, with the raising of London Circuit nearing completion, construction of the trackwork for Stage 2A commenced under a $577 million government contract with Capital Metro.[86][87] The extension is expected to be operational by early 2028.[88][3]

Stage 2B

[edit]

Consideration of route options

[edit]

Stage 2B, if pursued, will cross over Commonwealth Avenue Bridge and then travel to Woden predominately via Adelaide Avenue and Yarra Glen.

In May 2017, design options for several sections of the route (not yet divided between Stages 2A and 2B) were presented to the public for comment.[89][90] There were two options for the section between Lake Burley Griffin and Adelaide Avenue: a deviation to Barton with proposed stops at Old Parliament House, Brisbane Avenue and Sydney Avenue; or a more direct route via the Capital Circle.[91] An alternate terminus that would have extended the route to the Canberra Hospital was dropped in December 2017.

Route options for Stage 2 presented in May 2017
Map
Routes for the Woden extension presented in May 2017:
  Option 1 via State Circle (ultimately selected)
  Option 2 via Barton
  Alternative route through the city (not pursued)
  Alternative terminus at Canberra Hospital (not pursued)

The longer route via Barton (Option 2) was selected by the ACT Government as the preferred route in April 2018.[92] In March 2019, the Commonwealth Government offered its support for the extension to Woden, however, it favoured a different path around Capital Hill, arguing for a route along the State Circle (Option 1).[93] A delay in the federal government response meant planning work for the line was postponed, though choosing to not pursue the Barton route could mean a simpler regulatory process.[93]

In May 2026, following public consultation, the ACT Government announced that it had chosen the State Circle route (Option 1).[94][95] This will include the construction of a tunnel from Commonwealth Avenue to ease the gradient and curve for light rail vehicles entering State Circle.[96][97]

Business case and regulatory approvals process

[edit]

In 2018, prior to the splitting of Stages 2A and 2B, the ACT Government concluded that Option 1 of Stage 2 would cost $1,074.7 million and produce $589.5 million worth of benefits, whilst Option 2 would cost $1,008.4 million and produce $587.3 million worth of benefits.[98] The Government did not publish that report until 2025.[99]

The ACT Government's 2019 business case for Stage 2A included costs and benefit estimates for the whole of Stage 2.[100] Those estimates implied that Stage 2B would cost $905 million and would produce $1,067 million worth of benefits.

In July 2019, the ACT Government submitted a referral for Stage 2B to the Australian Department of Environment and Energy.[101]

Potential further extensions

[edit]

Stage 3: Belconnen to Canberra Airport

[edit]

In October 2019, the ACT Government released its infrastructure plan which included stage 3 of light rail going from Belconnen to Canberra Airport via Civic, with the Civic–Belconnen section built first.[102][103]

Stage 4: Woden to Tuggeranong

[edit]

In October 2019, the ACT Government released its infrastructure plan which included stage 4 extending from Woden to Tuggeranong via Mawson.[103]

Twenty-five-year vision

[edit]

In October 2015, the ACT Government released a plan for a citywide light rail network that would be built over twenty-five years.[104] The plan includes the following elements:[105]

Corridor Priority Notes
Gungahlin to City Complete Stage One
Parliamentary Triangle High Connecting City to Russell, City to the Parliamentary Zone and Russell to the Parliamentary Zone.
Woden to City High Running via Adelaide Avenue.
Tuggeranong to Woden (Athllon Corridor) Running either via the Athllon Drive Corridor or the existing rapid bus alignment along Erindale Drive
Eastern connections (Fyshwick and Canberra Airport) High Additions to the Parliamentary Triangle routes, from Russell to Canberra Airport and the Parliamentary Zone to Fyshwick.
Belconnen to City Running via Southern Cross Drive and Barry Drive
Molonglo to City Woden to City via Hindmarsh Drive, John Gorton Drive and Parkes Way

Political opposition and debate

[edit]
A protest against the light rail being constructed in March 2016

In April 2024, the Canberra Liberals proposed an alternative from the ACT Government’s plans to extend the light rail network between the City and Woden. Instead, they suggested the establishment of dedicated bus lanes along the same corridor, presenting it as a more practical and financially responsible alternative to the proposed rail system. This proposal aimed to address growing public concerns about the cost, feasibility and long-term implications of the light rail extension, sparking widespread debate about the future of Canberra’s transport infrastructure.[106][107]

The Canberra Liberals argued that dedicated bus lanes would deliver substantial improvements in public transport connectivity and efficiency while avoiding the high upfront costs associated with light rail construction. Unlike light rail, which requires extensive investment in fixed infrastructure such as tracks, overhead wiring and stations, dedicated bus lanes could be implemented using existing roads with comparatively minor modifications. This, they contended, would make the project more cost effective and achievable within a shorter timeframe.[106][107]

However, their proposal was not without its critics. Advocates of the light rail extension pointed to the long-term benefits of rail infrastructure, which they argued went beyond immediate transport needs. Light rail, they contended, has the potential to reshape urban development patterns by encouraging higher-density housing and commercial activity along its corridors. This, in turn, could reduce urban sprawl, lower carbon emissions and create more vibrant, walkable communities. Proponents also argued that light rail’s fixed infrastructure gives it an edge in attracting investment and instilling confidence in businesses and residents, who view it as a permanent and reliable form of transport.[106][107]

The Public Transport Association of Canberra described the Canberra Liberals busway plan as an "incredibly poor substitute", because there would be no dedicated bus lanes on Commonwealth Avenue, leaving buses still stuck in traffic, with no reliability improvements.[108]

Environmental considerations also played a role in the debate. While buses are increasingly adopting cleaner technologies such as electric and hydrogen fuel cells, light rail remains a zero-emission option powered by electricity. Supporters of the light rail extension highlighted its potential to reduce Canberra’s overall carbon footprint, contributing to the city’s ambitious climate change goals. They questioned whether a bus-based system could achieve the same level of sustainability in the long run.[106][107]

In its budget submission, Public Transport Association of Canberra expressed support for expanding the light rail network to include the airport. The association advocated for extensions as a means to reduce transport emissions and provide a sustainable, efficient travel option for airport passengers.[109]

References

[edit]
  1. ^ "Operational Performance". 31 October 2018.
  2. ^ a b "Sandford Street light rail stop now operational". ACT Government. 16 September 2021. Archived from the original on 27 September 2021. Retrieved 27 September 2021.
  3. ^ a b Bushnell, Ian. "Get ready: Start date revealed for Light Rail Stage 2A construction". Riotact. Retrieved 8 February 2025.
  4. ^ "On track: Government updates delivery plans for stage 2A". Canberra Weekly. 28 April 2021. Retrieved 11 May 2021.
  5. ^ "The Canberra Legacy: Griffin, Government and the Future of Strategic Planning in the National Capital" (PDF). Be.unsw.edu.au. p. 26. Retrieved 8 March 2015.
  6. ^ Stokes, HJW (1984). Railways of the Canberra and Monaro Districts. Canberra: Australian Railway Historical Society.
  7. ^ a b Light Rail for Canberra (PDF) (Report). Comeng. November 1988. Archived (PDF) from the original on 6 December 2025 – via ptcbr.org.
  8. ^ Downie, Graham (21 December 1994). "Govt pays fare for next light rail trip". The Canberra Times. Retrieved 12 June 2017.
  9. ^ Hull, Crispin (4 January 1995). "Light-rail to costly for ACT, say Libs". The Canberra Times. Retrieved 13 June 2017.
  10. ^ "Heritage Tramway proposed for Canberra" Trolley Wire issue 272 February 1998 page 16
  11. ^ "Greens MLA Shane Rattenbury supports Labor in the ACT to return Katy Gallagher as Chief Minister". news.com.au. 2 November 2012. Retrieved 7 October 2024.
  12. ^ Canberrans not completely on board light rail project: poll Canberra Times 3 August 2014
  13. ^ "Labor backs light rail". ABC News. 20 September 2012. Retrieved 13 February 2025.
  14. ^ "Light rail contract 'will be torn up' if the Canberra Liberals win 2016 ACT election". ABC News. 15 April 2015. Retrieved 15 April 2015.
  15. ^ "Light rail will dominate next year's ACT election. Both main parties have more explaining to do". The Canberra Times. 11 October 2015.
  16. ^ Knaus, Christopher (15 October 2016). "Election win shows comprehensive support for light rail". The Canberra Times.
  17. ^ "ACT election: Labor Chief Minister Andrew Barr claims victory, says Canberra has voted for light rail". ABC News. 15 October 2016. Retrieved 15 October 2016.
  18. ^ "Canberra light rail funding included in budget". Railway Gazette International. 10 June 2013. Archived from the original on 15 June 2013. Retrieved 11 June 2013.
  19. ^ A Public Private Partnership for Canberra Metro Archived 2014-11-29 at the Wayback Machine Capital Metro
  20. ^ Canberra light rail project moves ahead after business case approved ABC News 16 September 2014
  21. ^ a b c d e f g "Capital Metro Contract Summary" (PDF). Transport Canberra and City Services. Archived (PDF) from the original on 21 March 2019. Retrieved 20 April 2019.
  22. ^ Canberra Metro selected to build stage one of light rail from Gungahlin to the city ABC News 1 February 2016
  23. ^ Capita Metro named as successful light rail consortium Archived 2016-02-29 at the Wayback Machine Canberra Metro 1 February 2016
  24. ^ a b "Contracts signed for Canberra's first light rail project". Capital Metro. 17 May 2016.[permanent dead link]
  25. ^ Sibthorpe, Clare (12 July 2016). "Construction begins on ACT light rail depot at Mitchell". The Canberra Times.
  26. ^ Canberra light rail contract signed Archived 20 December 2016 at the Wayback Machine Railway Gazette International 18 May 2016
  27. ^ Budget 2017: Extra safety inspectors announced for Canberra light rail Canberra Times 3 June 2017
  28. ^ Burgess, Katie (26 October 2018). "Canberra's light rail won't take passengers until 2019". The Canberra Times. Retrieved 7 November 2018.
  29. ^ "Transport Canberra and City Services: Annual Report 2016-17 Volume 1" (PDF). Transport Canberra and City Services Directorate. Archived (PDF) from the original on 21 March 2019. Retrieved 21 April 2019.
  30. ^ Burgess, Katie (12 June 2018). "In dead of night, Canberra's light rail vehicle emerges for testing". The Canberra Times. Retrieved 15 July 2018.
  31. ^ Canberra's last light rail vehicle arrives Canberra Times 27 September 2018
  32. ^ Burgess, Kate (19 March 2019). "Start date revealed for Canberra's light rail system". The Canberra Times. Retrieved 19 March 2019.
  33. ^ "Canberra light rail delivered in time for Easter launch". UGL. Retrieved 25 July 2024.
  34. ^ Jervis-Bardy, Dan (13 May 2019). "Canberra's light rail bill arrives at $675 million". The Canberra Times. Retrieved 2 June 2021.
  35. ^ a b "Capital Metro - Canberra's light rail: design drawings" (PDF). Arup/Hassell/Parsons Brinckerhoff/Capital Metro Agency. pp. 32, 33. Archived from the original (PDF) on 19 October 2016. Retrieved 17 October 2016.
  36. ^ "Find your stop". CMET. 6 September 2018. Retrieved 27 September 2021.
  37. ^ "Light Rail Stage 1 takes shape as stop names announced". Transport Canberra. Archived from the original on 14 April 2018. Retrieved 5 May 2017.
  38. ^ "Capital Metro - Canberra's light rail: design drawings" (PDF). Arup/Hassell/Parsons Brinckerhoff/Capital Metro Agency. p. 8. Archived from the original (PDF) on 19 October 2016. Retrieved 17 October 2016.
  39. ^ "Capital Metro - Canberra's light rail: design drawings" (PDF). Arup/Hassell/Parsons Brinckerhoff/Capital Metro Agency. p. 10. Archived from the original (PDF) on 19 October 2016. Retrieved 17 October 2016.
  40. ^ "Capital Metro - Canberra's light rail: design drawings" (PDF). Arup/Hassell/Parsons Brinckerhoff/Capital Metro Agency. p. 13. Archived from the original (PDF) on 19 October 2016. Retrieved 17 October 2016.
  41. ^ "Capital Metro - Canberra's light rail: design drawings" (PDF). Arup/Hassell/Parsons Brinckerhoff/Capital Metro Agency. pp. 15, 16. Archived from the original (PDF) on 19 October 2016. Retrieved 17 October 2016.
  42. ^ "Capital Metro - Canberra's light rail: design drawings" (PDF). Arup/Hassell/Parsons Brinckerhoff/Capital Metro Agency. p. 43. Archived from the original (PDF) on 19 October 2016. Retrieved 17 October 2016.
  43. ^ "Capital Metro - Canberra's light rail: design drawings" (PDF). Arup/Hassell/Parsons Brinckerhoff/Capital Metro Agency. p. 25. Archived from the original (PDF) on 19 October 2016. Retrieved 17 October 2016.
  44. ^ "Capital Metro - Canberra's light rail: design drawings" (PDF). Arup/Hassell/Parsons Brinckerhoff/Capital Metro Agency. p. 27. Archived from the original (PDF) on 19 October 2016. Retrieved 17 October 2016.
  45. ^ "Capital Metro - Canberra's light rail: design drawings" (PDF). Arup/Hassell/Parsons Brinckerhoff/Capital Metro Agency. p. 44. Archived from the original (PDF) on 19 October 2016. Retrieved 17 October 2016.
  46. ^ "Capital Metro - Canberra's light rail: design drawings" (PDF). Arup/Hassell/Parsons Brinckerhoff/Capital Metro Agency. p. 36. Archived from the original (PDF) on 19 October 2016. Retrieved 17 October 2016.
  47. ^ "Capital Metro - Canberra's light rail: design drawings" (PDF). Arup/Hassell/Parsons Brinckerhoff/Capital Metro Agency. p. 37. Archived from the original (PDF) on 19 October 2016. Retrieved 17 October 2016.
  48. ^ "Capital Metro - Canberra's light rail: design drawings" (PDF). Arup/Hassell/Parsons Brinckerhoff/Capital Metro Agency. p. 40. Archived from the original (PDF) on 19 October 2016. Retrieved 17 October 2016.
  49. ^ "Capital Metro - Canberra's light rail: design drawings" (PDF). Arup/Hassell/Parsons Brinckerhoff/Capital Metro Agency. p. 41. Archived from the original (PDF) on 19 October 2016. Retrieved 17 October 2016.
  50. ^ Brewer, Peter (4 June 2019). "More buses arriving and Mitchell lands a second light rail stop". The Canberra Times. Australian Community Media. Retrieved 8 November 2019.
  51. ^ New light rail stop in Mitchell Transport Canberra
  52. ^ "Corrs Advises Pacific Partnerships And John Holland On Canberra's Light Rail Project". Corrs Chambers Westgarth Laweyers. 24 February 2016. Archived from the original on 20 March 2019. Retrieved 20 April 2019.
  53. ^ a b c d e Capital Metro Agency (1 June 2016). "Capital Metro Contract Summary" (PDF). Transport Canberra City Services. Archived from the original (PDF) on 21 March 2019. Retrieved 21 December 2019.
  54. ^ "Canberra Light Rail". www.pacificpartnerships.com.au. Archived from the original on 20 December 2019. Retrieved 20 December 2019.
  55. ^ ASIC Company Registry; ACN 612 397 485
  56. ^ Hitch, Georgia (20 April 2019). "Canberra's light rail welcomes its first official passengers". ABC News. Retrieved 20 December 2019.
  57. ^ "Canberra Metro named as successful light rail consortium". ACT Government. Archived from the original on 1 April 2016. Retrieved 26 March 2016.
  58. ^ "CAF to deliver Capital Metro Trams" Railway Digest September 2016 page 4
  59. ^ "CAF awarded the supply of Canberra trams, in Australia". Construcciones y Auxiliar de Ferrocarriles. 1 February 2016.
  60. ^ First tram gets police escort into Canberra under the cover of darkness Canberra Times 14 December 2017
  61. ^ First tram arrives in Canberra Metro Report International 15 December 2017
  62. ^ A century late, Canberra gets its first tram Rail Express 15 December 2017
  63. ^ New ACTION buses to be blue, light rail trams to be red Archived 2016-12-20 at the Wayback Machine Canberra Times 14 December 2016
  64. ^ "Nuts and bolts". ACT Government. Archived from the original on 22 March 2016. Retrieved 26 March 2016.
  65. ^ a b Bushnell, Ian. "New battery-powered light rail vehicles slip quietly into service". Riotact. Retrieved 20 January 2025.
  66. ^ "Light Rail Innovation | News & Insights". Informa Australia. 10 February 2017. Retrieved 28 May 2020.
  67. ^ Staff Writer (24 February 2020). "One-stop-shop for LRV operations". Rail Express. Retrieved 28 May 2020.
  68. ^ Carter, Mark (9 February 2015). "Canberra expands light rail project". International Railway Journal.
  69. ^ McIlroy, Tom (10 September 2015). "Underground power plan for Russell light rail extension". The Canberra Times.
  70. ^ Knaus, Christopher (7 June 2016). "ACT Budget 2016: Budget shows 'rubbish' claims on tram cost, chief minister says". The Canberra Times.
  71. ^ Lawson, Kirsten (21 July 2016). "Labor announces possible Canberra light rail extensions to build in next term of government". The Canberra Times.
  72. ^ Knaus, Christopher (2 September 2016). "Labor announces light rail to go to Woden". The Canberra Times.
  73. ^ "Canberra light rail's second stage to link Woden and Civic, ACT Government says". ABC News. Australian Broadcasting Corporation. 2 September 2016.
  74. ^ Lawson, Kirsten (25 November 2016). "Serious work to begin on Woden light rail line as ACT government calls tenders on design and cost". The Canberra Times.
  75. ^ Ian Bushnell (5 July 2019). "Light rail Stage 2 split in two in bid for faster approval". RiotACT. Region Group Pty Ltd. Retrieved 17 September 2019.
  76. ^ Hayne, Jordan (10 September 2019). "Canberra light rail's business plan for Stage 2A approved by ACT Government, London Circuit to be raised". ABC.net.au. Australian Broadcasting Corporation. Retrieved 17 September 2019.
  77. ^ "Raising London Circuit". The Canberra Times. 27 July 2023. Retrieved 22 November 2023.
  78. ^ Major Projects Canberra (August 2019). "City to Woden Light Rail: Stage 2A City to Commonwealth Park Business Case" (PDF). Transport Canberra. ACT Government. Archived from the original (PDF) on 24 February 2021. Retrieved 17 September 2019.
  79. ^ Fuller, Nicholas (24 September 2021). "Auditor-General: Light rail 2A will cost more than government claims". Canberra Daily. Retrieved 18 September 2025.
  80. ^ Bushnell, Ian. "Election clock is TikTok-ing for Canberra Liberals". Riotact. Retrieved 8 February 2025.
  81. ^ "Still haven't decided where your vote's going this ACT election? This might help". ABC News. 12 October 2020. Retrieved 8 February 2025.
  82. ^ "The ACT's new political strongholds emerge in breakdown of election results". ABC News. 4 November 2020. Retrieved 8 February 2025.
  83. ^ "Rethink your routine: London Circuit to close from 2 December". ACT Government. 22 November 2022. Retrieved 22 November 2023.
  84. ^ Twyford, Lottie. "UPDATED: 'Ludicrous' to suggest buses won't be changed after light rail gets to Woden: Steel". Riotact. Retrieved 22 November 2023.
  85. ^ Fenwicke, Claire. "Active travel lane openings, car park closures on the way as city centre revival moves ahead". Region Canberra. Retrieved 18 September 2025.
  86. ^ "Date set for light rail extension work as major disruption expected". www.canberratimes.com.au. 22 January 2025. Retrieved 8 February 2025.
  87. ^ Bushnell, Ian. "Light rail Stage 2A contract signed but it'll be 2028 before first passengers". Region Canberra. Retrieved 18 September 2025.
  88. ^ Bushnell, Ian. "Light rail Stage 2A contract signed but it'll be 2028 before first passengers". Riotact. Retrieved 3 January 2024.
  89. ^ Scott, Elise (1 May 2017). "Could Canberra's light rail head to Barton instead of Parliament House?". ABC News. Australian Broadcasting Corporation.
  90. ^ Kirsten, Lawson (2 May 2017). "Canberra light rail: Options for stage two route to Woden revealed". The Canberra Times. Retrieved 10 April 2018.
  91. ^ Burgess, Katie (19 December 2017). "Canberra Hospital extension officially dropped for stage two of light rail". The Canberra Times. Retrieved 10 April 2018.
  92. ^ Trask, Steven (19 April 2018). "ACT government announces preferred stage two light rail route". The Canberra Times. Retrieved 19 April 2018.
  93. ^ a b Burgess, Katie (7 March 2019). "Commonwealth backs State Circle route for light rail stage two". The Canberra Times. Retrieved 27 April 2019.
  94. ^ "Canberra's light rail to Woden to take more-direct route after feedback". ABC News. 3 May 2026. Retrieved 17 May 2026.
  95. ^ Bushnell, Ian. "State Circle it is for light rail to Woden, but there are changes". Region Canberra. Retrieved 17 May 2026.
  96. ^ Connor, Coquohalla (7 July 2025). "New vision shows how Canberra light rail would transform key roundabout". ABC News. Retrieved 7 January 2026. " The fly-over vision also shows the planned tunnel, which would be constructed close to Parliament House, before re-emerging onto State Circle. Last year, the government said the short tunnel under Commonwealth Avenue could address engineering challenges posed by a tight bend in its preferred route for light rail to Woden. Under the proposal, the track would descend into a cut-and-cover tunnel from the Commonwealth Avenue median near Parliament, before passing under Commonwealth Avenue to emerge on State Circle."
  97. ^ Coleman, James. "Inside the plans for new light rail tunnel". Region Canberra. Retrieved 17 May 2026.
  98. ^ Transport Canberra and City Services - Light Rail Stage 2 Business Case, January 2018
  99. ^ Stanhope, Jon (17 June 2025). "Tram plans the government didn't want you to see". Canberra CityNews. Retrieved 19 July 2025.
  100. ^ Corporate=, ACT Government;; PositionTitle=Director; SectionName=ACT Audit Office (26 June 2025). "Reports". www.audit.act.gov.au. Retrieved 19 July 2025.{{cite web}}: CS1 maint: multiple names: authors list (link)
  101. ^ "CMTEDD ACT PROCUREMENT/Transport - Land/Road reserves of Commonwealth Ave, State Circle, Adelaide Ave, Yarra Glen and Callam St/Australian Capital Territory/Commonwealth Park to Woden Light Rail Project, ACT". Department of the Environment and Energy. Retrieved 17 September 2019.
  102. ^ Bushnell, Ian (17 October 2019). "Belco, Airport and Tuggeranong next stops for Canberra's light rail journey". RiotACT. Region Group Pty Ltd. Retrieved 8 November 2019.
  103. ^ a b "Infrastructure Plan" (PDF). ACT Treasury. ACT Government. Retrieved 8 November 2019.
  104. ^ McIlroy, Tom (26 October 2015). "Woden and Parliament next for light rail lines in Canberra tram master plan". The Canberra Times.
  105. ^ "Light Rail Network - Delivering a modern transport system for a growing city". ACT Government/Trove. 2015. Retrieved 18 June 2019.
  106. ^ a b c d "Canberra Liberals announce people focused public transport policy". Canberra Daily. 3 April 2024. Retrieved 3 April 2024.
  107. ^ a b c d "Canberra Liberals' proposed public transport plan would see a busway replace light rail with locally built electric buses". ABC News. 3 April 2024. Retrieved 3 April 2024.
  108. ^ secretary (9 June 2024). "Canberra Liberals admit busway plan is a no-go". Public Transport Association of Canberra. Retrieved 11 January 2026.
  109. ^ "Future Light Rail Network". Public Transport Association of Canberra. Retrieved 13 January 2024.
[edit]

Wikimedia Commons logo Media related to Canberra Metro at Wikimedia Commons